MCR-4996-003 |
| Project Description: | This is an existing paved road that is to be widened to a five lane roadway. This project may include grade, drain, base, pave, resurfacing, widening, shoulder work, curb and gutter, pavement markings and Right-of-Way acquisition. |
| Project Length: | 2.0 miles. |
| Project Estimate: | $7,000,000.00 (80% Federal Funds - 20% County Funds) |
| Project Status: | ALDOT Project - Design 70% Complete - Acquiring ROW. |
| Consultant Engineer: | Baskerville Donovan, Inc. |
| Consultant Phone: | 251-380-0311 |