MCR-4996-116


Project Description: These are existing dirt roads that are to be cleared, grubbed, graded, drained, based and paved. This project may include additional Right-of-Way, drainage improvements and pavement markings.
Project Length: 1.1 miles.
Project Estimate: $364,620.00
Project Status: Part A) Richard Weaver Road - Construction 100% complete.//// Part B) Rester & Coleman: Soshee Road - ROW Acquisition & Utility Relocation..
Consultant Engineer: Rester & Coleman Engineers Inc.
Consultant Phone: 251-479-4518

Richard Weaver Road

116a
VICINITY MAP, N.T.S.

Byrd Pit Road West, Byrd Pit Road East, & Soshee Road

116b

VICINITY MAP, N.T.S.