MCR-2000-007

Project Description: ADL: ADDITIONAL LANES - This is an existing road that is to have additional lanes. This may include patching, leveling, resurfacing, shoulder work, traffic control installation, intersection improvements, drainage improvements, utility relocations and right of way and/or drainage easement acquisition.
Project Length: 5.5 miles.
Project Estimate: $2,700,000.00
Project Status: Thompson Engineering: Design Complete - ROW Complete - Utility Relocation .
Consultant Engineer: Harper & Garratt Engineering
Consultant Phone: 251-675-7887

Celeste Rd

007




Mobile County Public Works - Engineering Department


BACK TO PAY-AS-YOU-GO PROJECTS INDEX