MCR-2004-008


Project Description: ADL: ADDITIONAL LANES- This is an existing road that will be widened to three lanes. This may include patching, leveling, resurfacing, shoulder work, traffic control installation, intersection improvements, drainage improvements, utility relocations and right of way and/or drainage easement acquisition.
Project Length: 2.6 miles.
Project Estimate: $2,750,000.00 ( Funded with County 2004 Pay As You Go Funds)
Project Status: BDI: Design Complete - Acquiring ROW - See project MCR-2006-010.
Consultant Engineer: Baskerville-Donovan, Inc.
Consultant Phone: 251-380-0311

Cody Rd.

008
VICINITY MAP, N.T.S.



Mobile County Public Works - Engineering Department


PAYG Navigation

COUNTY WIDE | DISTRICT 1 | DISTRICT 2 | DISTRICT 3
BACK TO PAY-AS-YOU-GO PROJECTS INDEX