MCR-2004-009


Project Description: GDBP: GRADE, DRAIN, BASE & PAVE- A section of this project includes new road construction and a section includes additional lanes to an existing road that is to be cleared, grubbed, graded, drained, based & paved. This project may include clearing, grubbing, grade, drain, base, pave, guardrail, intersection improvements, pavement markings, utility relocations and right of way and/or drainage easement acquisition.
Project Length: 1.7 miles.
Project Estimate: $2,500,000.00 ( Funded with County 2004 Transportation Pay As You Go Funds)
Project Status: McCrory & Williams: Desing 90% Complete - Acquiring ROW.
Consultant Engineer: McCrory & Williams, Inc.
Consultant Phone: 251-476-4720