| Project Description: | GDBP: GRADE, DRAIN, BASE & PAVE - These are existing dirt roads that are to be cleared, grubbed, graded, drained, based & paved. This project may include clearing, grubbing, grade, drain, base, pave, guardrail, intersection improvements, pavement markings, utility relocations and right of way and/or drainage easement acquisition. |
| Project Length: | 0.9 miles. |
| Project Estimate: | $565,000.00 |
| Project Status: | Design 80% Complete . |
| Consultant Engineer: | Goodwyn, Mills & Cawood, Inc. |
| Consultant Phone: | 251-271-3200 |
| Saraland Streets | |
| Sidney Dr | Airport Rd |
| Pauline St | Holcome St |
|
MAP 1 of 2; Project GDBP: GRADE, DRAIN, BASE & PAVE |
|
| Saraland Streets | |
| Glenway Dr | Oak Springs Dr |
|
MAP 2 of 2; Project GDBP: GRADE, DRAIN, BASE & PAVE |
|