| Project Description: | GDBP: GRADE, DRAIN, BASE & PAVE - These are existing dirt roads that are to be cleared, grubbed, graded, drained, based & paved. This project may include clearing, grubbing, grade, drain, base, pave, guardrail, intersection improvements, pavement markings, utility relocations and right of way and/or drainage easement acquisition. |
| Project Length: | 1.3 miles. |
| Project Estimate: | $880,000.00 |
| Project Status: | Kellogg Brown & Root//Design Complete - ROW acquision complete - Utility Relocation. . |
| Consultant Engineer: | Kellogg, Brown, & Root, Inc. |
| Consultant Phone: | 251-450-7000 |
| Rock Rd | |
|
MAP 1 of 2; Project GDBP: GRADE, DRAIN, BASE & PAVE |
| David Dr | |
| Smith Rd | |
| George Cir | |
|
MAP 2 of 2; Project GDBP: GRADE, DRAIN, BASE & PAVE |