Mobile County
Commission 2004 TRANSPORTATION
PAY-AS-YOU-GO PROGRAM DISTRICT ONE PROJECTS
Project # / Road
Name |
Begin Project |
End Project |
Length (MI)* |
Type of Work |
Estimate |
| Click Project Number for
Details |
| MCR-2004-101 |
|
|
|
|
|
| B STREET |
G STREET |
1690 FT SOUTH OF G STREET |
0.3 |
GDBP |
|
| C STREET |
B STREET |
MARTIN LUTHER KING JR AVE |
0.2 |
GDBP |
|
| D STREET |
C STREET |
E STREET |
0.1 |
GDBP |
|
| E STREET |
B STREET |
460 FT EAST OF B STREET |
0.1 |
GDBP |
|
| F STREET |
B STREET |
312 FT EAST OF B STREET |
0.1 |
GDBP |
|
| |
TOTAL
LENGTH (MILES): |
0.8 |
TOTAL ESTIMATED
COST: |
750,000.00 |
| MCR-2004-102 |
|
|
|
|
|
| BESSEMER AVENUE HOUSING CANADA AVENUE |
MAIN ST |
MAGEE ST |
0.2 |
WSO |
|
| BESSEMER AVENUE HOUSING HINSON AVENUE |
260 FT EAST OF WISCONSIN ST |
150 FT WEST OF THEATRE AVE |
0.2 |
WSO |
|
| BESSEMER AVENUE HOUSING LINCOLN AVENUE |
WISCONSIN ST |
MAIN ST |
0.3 |
WSO |
|
| BESSEMER AVENUE HOUSING MAGEE STREET |
LINCOLN AVE |
BESSEMER AVE |
0.2 |
WSO |
|
| BESSEMER AVENUE HOUSING PERSONS STREET |
LINCOLN AVE |
CANADA AVE |
0.1 |
WSO |
|
| BESSEMER AVENUE HOUSING STREET 1 |
WISCONSIN ST |
THEATRE AVE |
0.1 |
WSO |
|
| BESSEMER AVENUE HOUSING STREET 2 |
CANADA AVE |
LINCOLN AVE |
0.1 |
WSO |
|
| BESSEMER AVENUE HOUSING THEATRE AVENUE |
THOMAS AVE |
LINCOLN AVE |
0.4 |
WSO |
|
| BESSEMER AVENUE HOUSING WISCONSIN STREET |
LINCOLN AVE |
THEATRE AVE |
0.3 |
WSO |
|
| ELDERLY VILLAGE STREET A |
MAIN ST |
825 FT EAST OF MAIN ST |
0.2 |
WSO |
|
| ELDERLY VILLAGE STREET B |
MAIN ST |
BESSEMER AVE |
0.1 |
WSO |
|
| ELDERLY VILLAGE STREET C |
STREET A |
STREET B |
0.1 |
WSO |
|
| NORWOOD POINTE ELLA AVENUE |
440 FT NORTH OF HATTIE LN |
1890 FT NORTH OF HATTIE LN |
0.3 |
WSO |
|
| NORWOOD POINTE STREET 1 |
ELLA AVE |
STREET 2 |
0.1 |
WSO |
|
| NORWOOD POINTE STREET 2 |
300 FT SOUTH OF STREET 1 |
580 FT NORTH OF STREET 1 |
0.2 |
WSO |
|
| NORWOOD POINTE STREET 3 |
ELLA AVE |
1080 FT EAST OF ELLA AVE |
0.2 |
WSO |
|
| SHELTON BEACH HOMES STREET 1 |
SHELTON BEACH RD |
870 FT SOUTH OF SHELTON BEACH RD |
0.2 |
WSO |
|
| SHELTON BEACH HOMES STREET 2 |
STREET 1 |
270 FT EAST OF STREET 1 |
0.1 |
WSO |
|
| SHELTON BEACH HOMES STREET 3 |
SHELTON BEACH RD |
720 FT SOUTH OF SHELTON BEACH RD |
0.1 |
WSO |
|
| SHELTON BEACH HOMES STREET 4 |
SHELTON BEACH RD |
STREET 3 |
0.2 |
WSO |
|
| SUBDIVISION OF PARKWOOD STREET 1 |
HIGHPOINT BLVD |
500 FT EAST OF HIGHPOINT BLVD |
0.1 |
WSO |
|
| SUBDIVISION OF PARKWOOD STREET 2 |
HIGHPOINT BLVD |
500 FT EAST OF HIGHPOINT BLVD |
0.1 |
WSO |
|
| |
TOTAL
LENGTH (MILES): |
3.9 |
TOTAL ESTIMATED
COST: |
350,000.00 |
| MCR-2004-103 |
|
|
|
|
|
| AMHURST DRIVE |
HIGHPOINT BLVD |
BRUNSWICK DR |
0.3 |
R |
|
| BELLMEADE DRIVE |
TRUETT ST |
END OF PAVEMENT |
0.3 |
R |
|
| BROADWAY BOULEVARD |
COAL ST |
MYRTLEWOOD BLVD |
0.1 |
R |
|
| COMMUNITY ROAD |
DOSSETT RD |
END OF ROAD |
0.1 |
GDBP |
|
| DADE STREET |
PERCY AVE |
OMEGA AVE |
0.2 |
R |
|
| DAVIS STREET |
WHISTLER AVE |
VIGOR AVE |
0.1 |
R |
|
| DAYTON AVENUE |
CHURCH ST |
BELLA ST |
0.2 |
R |
|
| DYKES ROAD |
WHISTLER ST |
TERMINAL ST |
0.6 |
R |
|
| FOREST PARK DRIVE |
HIGHPOINT BLVD |
BRUNSWICK DR |
0.2 |
R |
|
| GILMER AVENUE |
DIAL ST |
SALEM ST |
0.2 |
R |
|
| GLEN EAGLE COURT |
GLEN EAGLE DR |
END OF PAVEMENT |
0.1 |
R |
|
| GLEN EAGLE DRIVE |
HIGHPOINT BLVD |
PINEHURST DR |
0.2 |
R |
|
| HERMAN AVENUE |
W TURNER RD |
END OF PAVEMENT |
0.1 |
R |
|
| JARRELL DRIVE |
ATMORE AVE S |
HWY 45 |
0.2 |
R |
|
| LEEDS AVENUE N |
WARREN ST |
W TURNER RD |
0.3 |
R |
|
| LYRIC STREET |
RICH AVE |
ROSEDALE AVE |
0.1 |
R |
|
| MAGEE STREET |
CLARK AVE |
END OF PAVEMENT |
0.2 |
R |
|
| MYRTLEWOOD BOULEVARD |
BROADWAY BLVD |
END OF PAVEMENT |
0.2 |
R |
|
| NORTH STREET |
WILSON AVE |
SWEENEYS LN W |
0.2 |
R |
|
| OMEGA AVENUE |
DADE ST |
END OF PAVEMENT |
0.2 |
R |
|
| PERCY AVENUE |
MAIN ST |
DADE ST |
0.1 |
R |
|
| PRICE AVENUE |
MAIN ST |
DADE ST |
0.1 |
R |
|
| PRICE AVENUE |
DADE ST |
I-165 RIGHT-OF-WAY |
0.3 |
R |
|
| RAMONA STREET |
SEMINOLE ST |
PALMETTO AVE |
0.1 |
R |
|
| REBEL ROAD |
PRICE AVE S |
JOSEPH AVE N |
0.2 |
R |
|
| ROOSEVELT STREET |
FIRST AVE |
RICH AVE |
0.1 |
R |
|
| SEMLER STREET |
TELEGRAPH RD |
END OF PAVEMENT |
0.3 |
R |
|
| TALLAPOOSA STREET |
SEMINOLE ST |
PALMETTO AVE |
0.1 |
R |
|
| TRAVIS AVENUE |
ALBERT REESE ST |
DIAZ ST |
0.1 |
R |
|
| TRUETT STREET |
ATMORE AVE S |
LEEDS AVE S |
0.2 |
R |
|
| VINEWOOD DRIVE |
BEARFORK RD |
END OF PAVEMENT |
0.1 |
R |
|
| WARREN PLACE |
LEEDS AVE N |
WARREN ST |
0.1 |
R |
|
| WASHAM STREET |
FIRST ST |
RICH AVE |
0.1 |
R |
|
| WECO STREET |
BEARFORK RD |
GILMER AVE |
0.2 |
R |
|
| |
TOTAL LENGTH (MILES): |
6.2 |
TOTAL ESTIMATED COST: |
1,500,000.00 |
| MCR-2004-104 |
|
|
|
|
|
| FIFTH STREET |
YEEND AVE |
SECOND ST |
0.4 |
R |
|
| FIFTH STREET (E/W ALLEY) |
FIFTH ST |
SEVENTH ST |
0.1 |
R |
|
| LEE STREET ALLEY |
FIFTH ST |
YEEND AVE |
0.2 |
R |
|
| SUTHERLAND CIRCLE |
SUTHERLAND DR |
SUTHERLAND DR |
0.1 |
R |
|
| VIADUCT ROAD |
HOWELL ST |
NORFOLK SOUTHERN RAILROAD CROSSING |
0.5 |
R |
|
| WEST LEE STREET |
YEEND AVE |
S.W. BLVD |
0.2 |
R |
|
| WILSON AVENUE |
HWY 43 |
0.4 MILES SOUTH OF HWY 43 |
0.4 |
R |
|
| |
TOTAL LENGTH (MILES): |
1.9 |
TOTAL ESTIMATED COST: |
450,000.00 |
| MCR-2004-105 |
|
|
|
|
|
| AIRPORT ROAD |
CEDAR ST |
ROSEMONT DR |
0.3 |
GDBP |
|
| GLENWAY DRIVE |
END OF PAVEMENT |
CITY LIMITS |
0.1 |
GDBP |
|
| HOLCOMBE STREET |
BALDWIN ST |
PAULINE ST |
0.1 |
GDBP |
|
| OAK SPRINGS DRIVE |
KALI-OKA SPRINGS DR |
(NORTH) END OF MAINTENANCE |
0.2 |
GDBP |
|
| PAULINE STREET |
(SOUTH) END OF MAINTENANCE |
(NORTH) END OF MAINTENANCE |
0.1 |
GDBP |
|
| SIDNEY DRIVE |
CEDAR ST |
JOHN KIDD RD |
0.1 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
0.9 |
TOTAL ESTIMATED COST: |
565,000.00 |
| MCR-2004-106 |
|
|
|
|
|
| CEDAR STREET |
HILLTOP AVE |
BEGIN PAVEMENT |
0.4 |
GDBP |
|
| DALE DRIVE |
JUNIPER AVE |
CITY LIMITS |
0.1 |
GDBP |
|
| PAINTER DRIVE |
OAK AVE |
0.2 MILES SOUTH OF OAK AVE |
0.2 |
GDBP |
|
| SECOND STREET |
MAPLE AVE E |
END OF MAINTENANCE |
0.1 |
GDBP |
|
| SPAT BRIDGE (ON ORANGE AVENUE) |
O.1 MILE EAST OF MAGNOLIA AVE |
0.2 MILE EAST OF MAGNOLIA AVE |
0.1 |
BR |
|
| |
TOTAL LENGTH (MILES): |
0.9 |
TOTAL ESTIMATED COST: |
565,000.00 |
| MCR-2004-107 |
|
|
|
|
|
| BENTLEY ROAD SOUTH |
RIO HONDO DR |
END OF MAINTENANCE |
0.7 |
GDBP |
|
| I-65 SERVICE ROAD |
END OF STATE MAINTENANCE |
END OF PAVEMENT |
0.7 |
R |
|
| |
TOTAL LENGTH (MILES): |
1.4 |
TOTAL ESTIMATED COST: |
530,000.00 |
| MCR-2004-108 |
|
|
|
|
|
| DENNY STREET |
RAILROAD ST |
0.4 MILES SOUTH TO CURVE |
0.4 |
R |
|
| PARK STREET |
DUCLOUX RD |
OLD HWY 43 |
0.4 |
R |
|
| PIERCE STREET |
SPRING RD |
END OF PAVEMENT |
0.3 |
R |
|
| SIMISON STREET |
ST STEPHENS RD |
DUCLOUX RD |
0.2 |
R |
|
| ST STEPHENS ROAD |
OLD MILITARY RD |
OLD HWY 43 |
0.8 |
R |
|
| THOMPSON STREET |
OLD MILITARY RD |
END OF PAVEMENT |
0.1 |
R |
|
| |
TOTAL LENGTH (MILES): |
2.2 |
TOTAL ESTIMATED COST: |
450,000.00 |
| MCR-2004-109 |
|
|
|
|
|
| RUSSELL ROAD |
U. S. HWY 45 |
3980 FT WEST OF HWY 45 |
0.8 |
W&R |
|
| TRIUMP ROAD |
CENTER ST (CELESTE RD) |
1250 FT EAST OF CENTER ST (TO CEMETERY) |
0.2 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
1.0 |
TOTAL ESTIMATED COST: |
510,000.00 |
| MCR-2004-110 |
|
|
|
|
|
| ARMY ROAD |
END OF PAVEMENT |
WALTER MOORE RD |
1.0 |
GDBP |
|
| OLD CITRONELLE ROAD |
END OF PAVEMENT |
3750 FT NORTH |
0.7 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
1.7 |
TOTAL ESTIMATED COST: |
1,450,000.00 |
| MCR-2004-111 |
|
|
|
|
|
| WEAVER ROAD W |
WEAVER RD E |
END OF MAINTENANCE |
1.4 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
1.4 |
TOTAL ESTIMATED COST: |
1,070,000.00 |
| MCR-2004-112 |
|
|
|
|
|
| FRAZIER CEMETERY ROAD |
END OF PAVEMENT |
END OF MAINTENANCE |
0.4 |
GDBP |
|
| JERRY TAYLOR ROAD |
JOAN HARRIS RD |
END OF MAINTENANCE |
0.1 |
GDBP |
|
| JOAN HARRIS ROAD |
END OF PAVEMENT |
2200 FT SOUTH |
0.4 |
GDBP |
|
| ROBERT MARS ROAD |
FRAZIER CEMETERY RD |
END OF MAINTENANCE |
0.2 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
1.1 |
TOTAL ESTIMATED COST: |
860,000.00 |
| MCR-2004-113 |
|
|
|
|
|
| LAMBERT CEMETERY ROAD |
CELESTE RD |
3800 FT EAST OF CELESTE RD |
0.7 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
0.7 |
TOTAL ESTIMATED COST: |
630,000.00 |
| MCR-2004-114 |
|
|
|
|
|
| BEAR FORK ROAD |
U. S. HWY 45 |
MOFFETT RD |
4.3 |
R |
|
| |
TOTAL LENGTH (MILES): |
4.3 |
TOTAL ESTIMATED COST: |
860,000.00 |
| MCR-2004-115 |
|
|
|
|
|
| BELL DRIVE |
LONG RD |
HALL RD (PVT) |
0.3 |
GDBP |
|
| DALE DRIVE |
SATSUMA CITY LIMITS |
END OF MAINTENANCE |
0.1 |
GDBP |
|
| MARSHALL STREET |
OLD HWY 43 |
END OF MAINTENANCE |
0.2 |
GDBP |
|
| OLD U.S. HIGHWAY 43 |
SATSUMA CITY LIMITS |
SATSUMA CITY LIMITS |
0.4 |
GDBP |
|
| WILSON BOULEVARD |
END OF PAVEMENT |
END OF MAINTENANCE |
0.3 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
1.3 |
TOTAL ESTIMATED COST: |
890,000.00 |
| MCR-2004-116 |
|
|
|
|
|
| AVERETT ROAD |
ODOM RD |
END OF MAINTENANCE |
0.2 |
GDBP |
|
| JOHN PATRICK ROAD |
PATRICK RD |
END OF MAINTENANCE |
0.1 |
GDBP |
|
| PATRICK ROAD |
ODOM RD |
END OF MAINTENANCE |
0.6 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
0.9 |
TOTAL ESTIMATED COST: |
500,000.00 |
| MCR-2004-117 |
|
|
|
|
|
| COUNTRY ESTATES DRIVE |
SARALAND CITY LIMITS |
END OF MAINTENANCE |
0.4 |
GDBP |
|
| HENRY MORGAN ROAD |
KALI-OKA RD |
END OF MAINTENANCE |
0.4 |
GDBP |
|
| HERBERT MORGAN ROAD |
HENRY MORGAN RD |
END OF MAINTENANCE |
0.2 |
GDBP |
|
| JOYCE AVENUE N |
KUSHLA-MCLEOD RD |
END OF MAINTENANCE |
0.2 |
GDBP |
|
| OLD CITRONELLE HIGHWAY |
U. S. HWY 45 |
END OF MAINTENANCE |
0.3 |
GDBP |
|
| POWELL ROAD |
SPICE POND RD |
END OF MAINTENANCE |
0.3 |
GDBP |
|
| SMITHTOWN ROAD |
END OF PAVEMENT |
END OF MAINTENANCE |
0.1 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
1.9 |
TOTAL ESTIMATED COST: |
1,300,000.00 |
| MCR-2004-118 |
|
|
|
|
|
| RAMEY ROAD |
BEVERLY JEFFRIES HWY |
2694 FT NORTH OF BEVERLY JEFFRIES HWY |
0.5 |
GDBP |
|
| TANNER ROAD |
BEVERLY JEFFRIES HWY |
3500 FT SOUTH OF BEVERLY JEFFRIES HWY |
0.7 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
1.2 |
TOTAL ESTIMATED COST: |
730,000.00 |
| MCR-2004-119 |
|
|
|
|
|
| HARVILL ROAD N |
HARVILL RD |
SIMS ST |
0.1 |
GDBP |
|
| RAILROAD STREET E |
RAILROAD ST N |
RAILROAD ST S |
0.3 |
GDBP |
|
| RAILROAD STREET S |
U. S. HWY 43 |
HARVILL RD |
0.1 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
0.5 |
TOTAL ESTIMATED COST: |
300,000.00 |
| MCR-2004-120 |
|
|
|
|
|
| PATILLO ROAD |
WEST COY SMITH HWY |
END OF MAINTENANCE |
3.1 |
R |
|
| |
TOTAL LENGTH (MILES): |
3.1 |
TOTAL ESTIMATED COST: |
490,000.00 |
| MCR-2004-121 |
|
|
|
|
|
| HENRY DAVIS ROAD |
DURANGO DR |
END OF MAINTENANCE |
0.5 |
GDBP |
|
| HENRY DAVIS ROAD EXT |
HENRY DAVIS RD |
WEAVER RD W |
1.4 |
GDBP |
|
| |
TOTAL LENGTH (MILES): |
1.9 |
TOTAL ESTIMATED COST: |
1,500,000.00 |
| |
|
|
|
|
|
| PROJECT TOTALS |
LENGTH (MILES): |
39.2 |
ESTIMATED COST: |
16,250,000 |
MCR-2004-100 Projects - These are projects
that will be constructed within the boundaries of County Commission District
One and will be funded with $16,250,000 Mobile County 2004 Transportation
Pay-As-You-Go Funds. Project MCR-2004-101, City of Mobile Hope VI Project,
includes the construction funding for the wearing surface only for the streets
for the Federally Funded Housing Program. The Administration of the design and
construction of this project will be performed by the City of Mobile Housing
Authority. The project will be funded by the City of Mobile Housing Authority
with reimbursement by the 2004 Transportation Pay-As-You-Go Program Funds on a
road by road basis with a maximum reimbursement of $750,000. Project
MCR-2004-102, City of Prichard Hope VI Project, includes the construction
funding for several streets for the Federally Funded Housing Program. The
Administration of the design and construction of this project will be performed
by the Prichard Housing Authority. The project will be funded by the Prichard
Housing Authority with reimbursement by the 2004 Transportation Pay-As-You-Go
Funds on a road by road basis with a maximum reimbursement of $350,000.
| TYPE OF WORK DEFINITIONS |
| ADL: |
ADDITIONAL LANES
- This may include clearing, grubbing, grade, drain, base, pave, patching,
leveling, milling, resurfacing, shoulder work, traffic control installation,
intersection improvements, drainage improvements, utility relocations, and
right-of-way, and/or drainage easement acquisitions, and any other work
necessary for the completion of the project. |
| W&R: |
WIDENING AND
RESURFACING - This may include widening of existing pavement, patching,
leveling, milling, resurfacing, shoulder work, paving of a portion of the
shoulder, traffic control installation, intersection improvements, utility
relocation, and right-of-way and/or drainage easement acquisitions, and any
other work necessary for the completion of the project. |
| R: |
RESURFACE - This
may include patching, leveling, milling, resurfacing of the existing width of
paved road, minor drainage improvements, traffic control installation, utility
relocations, intersection improvements, and right-of-way and/or drainage
acquisitions, and any other work necessary for the completion of the
project. |
| GDBP: |
GRADE, DRAIN,
BASE & PAVE - This may include clearing, grubbing, grade, drain, base,
pave, guardrail, intersection improvements, pavement markings, utility
relocations, and right-of-way and/or drainage easement acquisitions, and any
other work necessary for the completion of the project. |
| BR: |
BRIDGE - This may
include clearing, grubbing, removal of old bridge, grade, drain, base, pave,
new bridge, pavement marking, utility relocation, and right-of-way, and any
other work necessary for the completion of the project. |
| WSO: |
WEARING SURFACE
ONLY - This may include the asphalt material and the labor and equipment to
install the asphalt wearing surface only. |
BACK TO TOP OF
PAGE
BACK TO TOP OF
PAGE |