Mobile County
Commission 2006 TRANSPORTATION
PAY-AS-YOU-GO PROGRAM
COUNTY-WIDE PROJECTS
Project
#/ Road Name |
Begin Project |
End Project |
Length (Mi)* |
Type of Work |
Estimate |
| Click Project Number for
Details |
| MCR-2006-001 |
|
|
|
|
|
| AIRPORT BLVD./SCHILLINGER RD. |
SIGNAL SYSTEM IMPROVEMENTS TO SEVERAL INTERSECTIONS IN THE AIRPORT BVLD. & SCHILLINGER RD. CORRIDOR |
SIGNAL SYSTEM IMPROVEMENTS TO SEVERAL INTERSECTIONS IN THE AIRPORT BVLD. & SCHILLINGER RD. CORRIDOR |
-- |
SSI |
|
| |
TOTAL LENGTH
(MILES): |
-- |
TOTAL ESTIMATED
COST: |
600,000.00 |
| MCR-2006-002 |
|
|
|
|
|
| AIRPORT BLVD. |
CODY RD. |
FLAVE PIERCE RD. |
2.7 |
R |
|
| |
TOTAL LENGTH
(MILES): |
2.7 |
TOTAL ESTIMATED
COST: |
2,000,000.00 |
| MCR-2006-003 |
|
|
|
|
|
| CELESTE RD. |
SALCO RD. |
CITRONELLE CITY LIMITS |
10.4 |
R |
|
|
TOTAL LENGTH
(MILES): |
10.4 |
TOTAL ESTIMATED
COST: |
3,230,000.00 |
| MCR-2006-004 |
|
|
|
|
|
| WILMER RD. |
TANNER WILLIAMS RD. |
U.S. 98 |
7.3 |
W&R |
|
| |
TOTAL LENGTH
(MILES): |
7.3 |
TOTAL ESTIMATED
COST: |
2,620,000.00 |
| MCR-2006-005 |
|
|
|
|
|
| BELLINGRATH RD. |
U.S. 90 |
AL 188 |
12.2 |
R |
|
| |
TOTAL LENGTH
(MILES): |
12.2 |
TOTAL ESTIMATED
COST: |
3,800,000.00 |
| MCR-2006-006 |
|
|
|
|
|
| CHUNCHULA GEORGETOWN RD. |
LOTT RD. |
U.S. 45 |
5.0 |
W&R |
|
| |
TOTAL LENGTH
(MILES): |
5.0 |
TOTAL ESTIMATED
COST: |
1,900,000.00 |
| MCR-2006-007 |
|
|
|
|
|
| SNOW RD. |
TANNER WILLIAMS RD. |
HOWELLS FERRY RD. |
2.1 |
R |
|
| |
TOTAL LENGTH
(MILES): |
2.1 |
TOTAL ESTIMATED
COST: |
1,000,000.00 |
| MCR-2006-008 |
|
|
|
|
|
| MCDONALD PADGETT SWITCH CONNECTOR RD. |
U.S. 90 |
HALF MILE RD. |
1.5 |
GDBP & BR |
|
| |
TOTAL LENGTH
(MILES): |
1.5 |
TOTAL ESTIMATED
COST: |
1,000,000.00
(Match Federal Funds)
|
| MCR-2006-009 |
|
|
|
|
|
| MCFARLAND RD |
COTTAGE HILL RD. |
DAWES LANE N. |
2.2 |
W&R |
940,000 |
| DAWES LANE N. |
MCFARLAND RD. |
DAWES RD. |
0.2 |
W&R |
60,000 |
| |
TOTAL LENGTH
(MILES): |
2.4 |
TOTAL ESTIMATED
COST: |
1,000,000.00 |
| MCR-2006-010 |
|
|
|
|
|
| CODY RD. |
COTTAGE HILL RD. |
PINE RUN RD. |
2.6 |
ADL |
|
| |
TOTAL LENGTH
(MILES): |
2.6 |
TOTAL ESTIMATED
COST: |
1,250,000.00
(Match 2004 TPAYGO Funds)
|
| |
|
|
|
|
| Projects |
TOTAL LENGTH
(MILES) |
46.2 |
ESTIMATED COST |
18,400,000 |
*Distances are to tenth of a mile
2006 TRANSPORTATION PROJECTS
The 2006 Transportation Projects were selected by the Commission for their benefit to the entire County regardless of the County Commission District in which they are located.
DESCRIPTION AND FUNDING FOR EACH PROJECT
Project MCR-2006-001 (Airport Blvd./Schillinger Rd. Signal System Improvements) Includes the professional engineering services for the signal-timing and corridor study of all intersections on Airport Boulevard from Alverson Road to the Airport Entrance Road and all intersections on Schillinger Road from Tanner Williams Road to Grelot Road. It will also include the installation of a new signal system recommended and designed from this data. This project will be funded by 2006 Transportation Pay-As-You-Go Funds.
Project MCR-2006-002 (Airport Boulevard) Includes the resurfacing of Airport Boulevard from Cody Road to Flave Pierce Road. This project will be funded by 2006 Transportation Pay-As-You-Go Funds.
Project MCR-2006-003 (Celeste Road) Includes the resurfacing of Celeste Road from Salco Road to the Citronelle City Limits. This project will be funded by 2006 Transportation Pay-As-You-Go Funds.
Project MCR-2006-004 (Wilmer Road) Includes the widening and resurfacing of Wilmer Road from Tanner Williams Road to U.S. 98. This project will be funded by 2006 Transportation Pay-As-You-Go Funds.
Project MCR-2006-005 (Bellingrath Road) Includes the resurfacing of Bellingrath Road from U.S. 90 to AL 188. This project will be funded by 2006 Transportation Pay-As-You-Go Funds.
Project MCR-2006-006 (Chunchula Georgetown Road) Includes the widening resurfacing of Chunchula Georgetown Road from Lott Road to U.S. 45. This project will be funded by 2006 Transportation Pay-As-You-Go Funds.
Project MCR-2006-007 (Snow Road) Includes the resurfacing of Snow Road from Tanner Williams Road to Howells Ferry Road with some profile grade improvements in areas determined during the design. This project will be funded with 2006 Transportation Pay-As-You-Go Funds.
Project MCR-2006-008 (McDonald Padgett Switch Connector Road) Includes the construction of a four lane divided road from U.S. 90 to Half Mile Road with a new bridge over U.S. 90 and CSX Railroad. This project will be funded with Federal Funds and County Match provided from 2000, 2004, and 2006 Transportation Pay-As-You-Go Funds.
Project MCR-2006-009 (McFarland Road and Dawes Lane North) Includes the widening and resurfacing of McFarland Road from Cottage Hill Road to Dawes Lane North and Dawes Lane North from McFarland Road to Dawes Road. This project will be funded with 2006 Transportation Pay-As-You-Go Funds.
Project MCR-2006-010 (Cody Road) Includes the widening of Cody Road from Cottage Hill Road to Pine Run Road to three lanes. This program will provide additional funds to match the funds provided in the 2004 Transportation Pay-As-You-Go Program for project MCR-2004-08.
| TYPE OF WORK DEFINITIONS |
| W&R: |
WIDEN AND RESURFACE - This may include widening of existing pavement, patching, leveling, milling, resurfacing, pavement marking, shoulder improvements, drainage improvements, guardrail, traffic control installation, intersection improvements, utility relocation, and right-of-way and/or drainage easement acquisitions, and any other work necessary for the completion of the project. |
| R: |
RESURFACE - This may include patching, leveling, milling, resurfacing of the existing width of paved road, pavement marking, minor drainage improvements, shoulder improvements, traffic control installation, utility relocations, intersection improvements, and right-of-way and/or drainage easement acquisitions, and any other work necessary for the completion of the project. |
| GDBP: |
GRADE, DRAIN, BASE & PAVE - This may include clearing, grubbing, grade, drain, base, pave, guardrail, intersection improvements, pavement markings, utility relocations, and right-of-way and/or drainage easement acquisitions, and any other work necessary for the completion of the project. |
| BR: |
BRIDGE - This may include clearing, grubbing, removal of old bridge, grade, drain, base, pave, new bridge, pavement marking, utility relocation, and right-of-way acquisition, and any other work necessary for the completion of the project. |
| ADL: |
ADDITIONAL LANES - This may include clearing, grubbing, grade, drain, base, pave, patching, leveling, milling, resurfacing, shoulder work, traffic control installation, intersection improvements, drainage improvements, utility relocations, and right-of-way, and/or drainage easement acquisitions, and any other work necessary for the completion of the project. |
| SSI: |
SIGNAL SYSTEM IMPROVEMENTS - This may include transportation signal timing and corridor studies replacement / removal of signal equipment; addition and/or upgrade of signal equipment; installation of signal system, video monitoring and detection equipment, and data acquisition equipment; installation of all programming and timing data to fulfill dynamic system changes to the corridors. |