Estimated 6 Month Bid Schedule

ESTIMATED 6 MONTH BID SCHEDULE OF ROAD, BRIDGE, AND DRAINAGE PROJECTS View the PDF

February-19

PROJECT NO.

DESCRIPTION

TYPE

TOTAL ESTIMATED PROJECT COST

APPROXIMATE BID DATE

CIP-2013-040

Mobile County Soccer Complex - Phase I

Park

$3,300,000

Feb-19

MCR-2016-308

Johnson Road W.

GDBP

$2,930,000

Feb-19

MCR-2016-009

Padgett Switch Road

RRR

$1,646,000

Feb-19

MCR-2014-106C

City of Prichard Streets (Elm Street E)

GDBP

$1,850,000

Mar-19

MCR-2008-004(B)

Schillinger Road at Silver Pine Road/Lamplighter Drive

Signalization

$250,000

Mar-19

MCR-2016-206

Randolph Foster Road

GDBP

$300,000

Apr-19

 

 

Total

$10,276,000

 

Other projects bidding within the next 3 - 6 months:

MCR-2010-305

Wright Road and Wright Alley

GDBP

$400,000

MCR-2014-307

Jackson Road, South Street & Pineview Avenue

GDBP

$1,423,000

MCR-2016-105

Mt. Vernon Streets

Resurfacing

$195,000

MCR-2010-310

Jeff Hamilton Road at Dawes Road

Roundabout

$1,700,000

MCR-2014-005

West Lake Road N

GDBP

$2,000,000

MCR-2014-006

Glass Road

GDBP

$2,500,000